Question 153:
A project has a ׀’׀׀¡ of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?
Answer options:
A. Add the required work to complete the project behind $892,500. B. Evaluate the impact and justify adding new work to the project. C. Obtain approval from the CCB.D. Request a budget increase of $170,000.