Question 236:

A project manager is procuring new equipment from a vendor. The vendor requires a physical signature on all purchase orders. Which of the following should the project manager do to order the equipment quickly? (Choose two.) 

Answer options:

A. Mail the purchase order and follow up with a phone call.
B. Fax the purchase order and follow up with a phone call.
C. Drive to the vendor if local and provide a signed purchase order.
D. Scan and send the purchase order and follow up with a phone call.
E. Request a courier from the vendor to pick up the purchase order.