Question 237:

Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project. Which of the following MOST likely explains this issue? 

Answer options:

A. Risks were not identified.
B. Risks were not mitigated.
C. Risks were not exploited.
D. Risks were not communicated.