Question 322:
A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?
Answer options:
A. Stakeholders B. Scrum master C. Project sponsor D. Project team