Question 323:
A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?
Answer options:
A. Change validation with quality checks B. Regression planning C. Identify approval authority D. Change implementation