Question 53:
Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
Answer options:
A. EAC B. BAC C. TCPI D. ETC
Answer correct:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232