Question 54:
A customer will have ongoing changes to project requirements. Which of the following is the BEST project management methodology for this requirement?
Answer options:
A. Waterfall B. Agile C. PRINCE2 D. Bottom-up
Answer correct:
B
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310