Question 8:
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints. Which of the following documents should the project manager use to obtain this information?
Answer options:
A. Project schedule B. Balanced scorecard C. Issue log D. Status report