CompTIA Project+ Exam Questions

CompTIA

CompTIA Project+

9 / 350

Question 9:

A stakeholder is unaware of a project`s status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.) 

Answer options:

A. Status report
B. Organizational chart
C. RACI matrix
D. Meeting minutes
E. Communication plan