Question 10:

There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks - A, B, F: 8 weeks - D, E, H: 12 weeks - D, B, F: 7 weeks - Which of the following tasks are on the critical path? 

Answer options:

A. A, C, G
B. A, B, F
C. D, E, H
D. D, B, F