Question 135:
A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.
Which of the following calculations accurately shows the critical path?
Answer options:
A. 20 days B. 39 days C. 49 days D. 52 days