Question 140:
A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?
Answer options:
A. Fast-track the tasks. B. Utilize positive float. C. Crash the schedule. D. Remove the critical path