Question 210:

A project has passed a phase-gate, and the new phase is ready to begin. Which of the following is the MOST appropriate method to communicate the transition to team? 

Answer options:

A. Kickoff meeting
B. One-on-one meetings
C. Voice conferencing
D. Instant messaging