Question 85:
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project`s resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference to fast-track the project? (Choose two.)
Answer options:
A. Scope management plan B. Configuration management plan C. Network diagram D. Project schedule E. Project plan