ExamQuestions.com

Register
Login
Certified in Risk and Information Systems Control Exam Questions

Isaca

Certified in Risk and Information Systems Control

70 / 500

Question 70:

Wendy has identified a risk event in her project that has an impact of $75,000 and a 60 percent chance of happening. Through research, her project team learns that the risk impact can actually be reduced to just $15,000 with only a ten percent chance of occurring. The proposed solution will cost $25,000. Wendy agrees to the $25,000 solution. What type of risk response is this? 

Answer options:

A. Mitigation
B. Avoidance
C. Transference
D. Enhancing