ExamQuestions.com

Register
Login
PRINCE2 Foundation Exam Questions

PRINCE2

PRINCE2 Foundation

125 / 230

Question 125:

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin? 

Answer options:

A. End Stage Report
B. Team Plan
C. Work Package
D. Project Plan