Question 140:

Why is a project brief produced? 

Answer options:

A. To act as a trigger for the `starting up a project` process
B. To record the how the project will communicate with its stakeholders
C. To provide a full and firm foundation for the initiation of a project
D. To be used by the project board as a basis for reviewing the progress of a project