Question 131:

While deciding on how the work of the project should be approached the following were considered. Which statement is appropriate for inclusion in the project approach heading in the Project Brief? 

Answer options:

A. The Project Manager will involve the selected service provider in the creation of the Stage Plan for stage 4.
B. New up-to-date software will be obtained to produce the graphical sections of the Project and Stage Plans.
C. The detailed designs (future process, systems, operating and organization models) will be based on the existing high-level designs.