ExamQuestions.com

Register
Login
PRINCE2 Practitioner Exam Questions

PRINCE2

PRINCE2 Practitioner

132 / 200

Question 132:

While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log. Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan? 

Answer options:

A. MFH has no experience in outsourcing and this may affect understanding of what is required, resulting in inadequate plans and strategies.
B. The Project Brief is a complex document and may not be approved by the Executive.
C. There is a shortage of service providers so there is a possibility that no suitable service providers respond to the request for proposals. This would prevent the Outsourcing project from proceeding.